The Route - Forman to Moorefield
July - September 2010 Status:
Construction
is underway along the 14.9-mile section from Forman to Moorefield. A 3-mile section
from US 220 to the WV 55 interchange was opened to traffic in November 2005.
Construction of two grade and drain contracts in Hardy County (one on each side
of the South Branch Potomac River) that began in September 2005 was completed in
early 2007, and in late summer 2007. The construction of the South Branch Potomac
River Bridge began in the fall of 2006 and is complete. Construction
of two additional grade and drain contracts in Grant and Hardy Counties, west of
the South Branch Potomac River, began in late summer 2006 and was completed in late
2008. The construction contract for a 10.4-mile paving project from Patterson Creek
to the South Branch Potomac River Bridge is underway and is anticipated to be complete in the fall of 2010.
The WVDOH anticipates that the Forman to Moorefield section will be open to traffic
in fall 2010.
This map is not to scale nor is it an accurate geographic representation of the area. This graphic is for planning and public information purposes only. Distances area approximated to the nearest alignment point.
The above graphic is a portion of the whole map. Please click here to view the entire map at full-size (135k).
If you would like a very detailed description of a certain area, please contact us and we will be happy to provide you with that information.
top of page
|
|
|
 |